| Design Registration (AB-500 Series) | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Form. No. | Document Name | Current Edition No. | Current Revision No. | Current Publication Date | Next Scheduled Reaffirmation | Responsible Position | Enabling Information Bulletin | Public Consultation Link |
Public Consultation Disposition Link |
| AB-520 |
Finite Element Analysis (FEA) Requirements Regarding the Use of FEA to Support a Pressure Equipment Design Submission | 2 | 0 | 2023-10-26 | 2028 | Design Survey Manager | IB23-046 | Sep 1, 2027 | Jun 1, 2028 |
| AB-521 |
Engineered Pressure Enclosures | 3 | 0 | 2024-10-10 | 2029 | Design Survey Manager | IB24-008 | Sep 1, 2028 | Jun 1, 2029 |
| AB-521a |
RRIMR Quality Plan Self-Evaluation and Application Form | 0 | 0 | 2024-10-10 | 2029 | Design Survey Manager | N/A | Sep 1, 2028 | Jun 1, 2029 |
| AB-525 |
Overpressure Protection Requirements for Pressure Vessel and Pressure Piping | 3 | 0 | 2025-10-17 | 2030 | Design Survey Manager | IB25-017 | Sep 1, 2029 | Jun 1, 2030 |
| AB-530 |
Quality Plan Requirements for Pressure Vessel Design Submissions | 2 | 0 | 2024-10-10 | 2029 | Design Survey Manager | IB24-007 | Sep 1, 2028 | Jun 1, 2029 |
| AB-531 |
Quality Plan Requirements for AB-OU Pressure Piping Design Submissions | 2 | 0 | 2024-10-10 | 2029 | Design Survey Manager | IB24-007 | Sep 1, 2028 | Jun 1, 2029 |
| AB-535 |
Requirements for Alteration Design Registration based on Fitness for Service Assessments | 3 | 0 | 2026-10-02 | 2031 | Design Survey Manager | IB26-006 | - | - |
| AB-536 |
Requirements for the Integrity Management of Grade 91 Steel Used Above Currently-Permitted Allowable Stresses | 2 | 0 | 2022-04-28 | 2027 | Assistant Chief Inspector, Technical Administration | IB22-005 | Sep 1, 2026 | Jun 1, 2027 |
| AB-539 |
Engineered Composite Systems for Pressure Equipment Alterations | 2 | 0 | 2024-10-10 | 2029 | Design Survey Manager | IB24-009 | Sep 1, 2028 | Jun 1, 2029 |
| Pressure Equipment Forms - 2. Construction and Installation (AB-500 Series) | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Form. No. | Document Name | Current Edition No. | Current Revision No. | Current Publication Date | Next Scheduled Reaffirmation | Responsible Position | Enabling Information Bulletin | Public Consultation Link | Public Consultation Disposition Link |
| AB-511 |
The Impact Testing Enigma | 4 | 0 | 2026-06-23 | 2031 | Manager of Inspections | N/A | - | - |
| AB-518 |
Pressure Piping Construction Requirements Document | 9 | 0 | 2022-09-19 | 2027 | Manager of Inspections | IB22-014 | Sep 1, 2026 | Jun 1, 2027 |
| AB-518a | AB518a replaced by AB-029b | ||||||||
| AB-518b |
Pressure Piping QMS Written Description Verification Checklist | 0 | 0 | 2026-07-17 | 2031 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-524 |
Pressure Relief Devices Requirements Document | 8 | 0 | 2026-07-09 | 2031 | Manager of Inspections | IB26-001 | - | - |
| AB-524b |
PRD QMS Written Description Certification Checklist | 0 | 0 | 2026-06-23 | 2031 | Manager of Inspections | N/A | - | - |
| AB-537 |
Thermal Liquid Heating System Requirements | 2 | 0 | 2023-05-05 | 2028 | Manager of Inspections | IB23-019 | Sep 1, 2027 | Jun 1, 2028 |
| AB-540 |
Quality Management System Requirements for Welder Performance Qualification Testing | 1 | 2 | 2026-07-13 | 2027 | Manager of Inspections | IB26-005 | Sep 1, 2026 | Jun 1, 2027 |
| AB-540a |
WPQ Testing Scope and Responsibilities | 1 | 0 | 2026-08-07 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-540b |
Welder Performance Qualification Testing Requirements QMS Manual Checklist | 0 | 0 | 2026-06-23 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-541 |
Quality Management System Requirements for Pressure Fitting Construction | 1 | 2 | 2026-07-13 | 2027 | Manager of Inspections | IB26-003 | Sep 1, 2026 | Jun 1, 2027 |
| AB-541a |
Pressure Fitting Construction Requirements QMS Manual & Audit Checklist | 0 | 0 | 2026-06-23 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-541b |
Pressure Fitting Construction Requirements QMS Manual & Audit Checklist | 0 | 0 | 2026-06-23 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| Pressure Equipment Forms - 3. Repair and Alteration (AB-500 Series) | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Form. No. | Document Name | Current Edition No. | Current Revision No. | Current Publication Date | Next Scheduled Reaffirmation | Responsible Position | Enabling Information Bulletin | Public Consultation Link | Public Consultation Disposition Link |
| AB-513 |
Pressure Equipment Repair and Alteration Requirements | 4 | 1 | 2023-12-08 | 2028 | Manager of Inspections | IB23-048 | Sep 1, 2027 | Jun 1, 2028 |
| AB-521 |
Requirements for Engineered Pressure Enclosures | 3 | 0 | 2024-10-10 | 2029 | Design Survey Manager | IB24-008 | Sep 1, 2028 | Jun 1, 2029 |
| AB-521a |
RRIMR Quality Plan Self-Evaluation and Application Form | 0 | 0 | 2024-10-10 | 2029 | Design Survey Manager | N/A | Sep 1, 2028 | Jun 1, 2029 |
| AB-523 |
Procedure Guideline for the Replacement of Mechanically Assembled Piping Components | 2 | 0 | 2022-10-31 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-536 |
Requirements for the Integrity Management of Grade 91 Steel Used Above Currently-Permitted Allowable Stresses | 2 | 0 | 2022-04-28 | 2027 | Assistant Chief Inspector, Technical Administration | IB22-005 | Sep 1, 2026 | Jun 1, 2027 |
| Pressure Equipment Forms - 4. In-Service Inspection (AB-500 Series) | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Form. No. | Document Name | Current Edition No. | Current Revision No. | Current Publication Date | Next Scheduled Reaffirmation | Responsible Position | Enabling Information Bulletin | Public Consultation Link | Public Consultation Disposition Link |
| AB-505 |
Risk-Based Inspection Requirements for Pressure Equipment | 4 | 0 | 2026-07-09 | 2031 | Manager of Inspections | IB26-002 | - | - |
| AB-506 |
Inspection and Servicing Requirements for In-Service Pressure Equipment | 4 | 0 | 2025-10-21 | 2030 | Manager of Inspections | IB25-019 | Sep 1, 2029 | Jun 1, 2030 |
| AB-507 |
Guidelines for the Inspection of Installed Fired Heaters | 0 | 3 | 2019-07-12 | None | Manager of Inspections | N/A | ||
| AB-512 |
Owner-User Pressure Equipment Integrity Management Requirements | 4 | 0 | 2025-10-14 | 2030 | Manager of Inspections | IB25-015 | Sep 1, 2029 | Jun 1, 2030 |
| AB-512a |
Owner-User PEIM Program Scope and Responsibilities | 0 | 0 | 2025-10-14 | 2030 | Manager of Inspections | N/A | Sep 1, 2029 | Jun 1, 2030 |
| AB-512b |
Integrity Management Requirements Checklist | 0 | 0 | 2026-06-23 | 2031 | Manager of Inspections | N/A | Sep 1, 2029 | Jun 1, 2030 |
| AB-512c |
PEIM Audit Workbook | 0 | 0 | 2025-10-14 | 2030 | Manager of Inspections | N/A | Sep 1, 2029 | Jun 1, 2030 |
| AB-512H |
Harmonized Requirements for Pressure Equipment Integrity Management Systems | 1 | 1 | 2026-07-13 | 2027 | Manager of Inspections | IB26-004 | Sep 1, 2026 | Jun 1, 2027 |
| AB-513 |
Pressure Equipment Repair and Alteration Requirements | 4 | 1 | 2023-12-08 | 2028 | Manager of Inspections | IB23-048 | Sep 1, 2027 | Jun 1, 2028 |
| AB-515 |
Quality Management System Requirements for Integrity Assessment Organizations | 3 | 0 | 2022-09-19 | 2027 | Manager of Inspections | IB22-013 | Sep 1, 2026 | Jun 1, 2027 |
| AB-515a |
Integrity Assessment Organization Authorized Scope Form | 0 | 0 | 2022-09-19 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-515b |
Integrity Assessment QMS Written Description Checklist | 0 | 0 | 2026-06-23 | 2031 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-519 |
Pressure Piping Alternative Test Methods Procedure Requirements | 3 | 0 | 2024-07-10 | 2029 | Manager of Inspections | IB24-005 | Sep 1, 2028 | Jun 1, 2029 |
| AB-521 |
Requirements for Engineered Pressure Enclosures | 3 | 0 | 2024-10-10 | 2029 | Design Survey Manager | IB24-008 | Sep 1, 2028 | Jun 1, 2029 |
| AB-521a |
RRIMR Quality Plan Self-Evaluation and Application Form | 0 | 0 | 2024-10-10 | 2029 | Design Survey Manager | N/A | Sep 1, 2028 | Jun 1, 2029 |
| AB-522 |
Standard Pneumatic Test Procedure Requirements for Piping Systems | 3 | 0 | 2023-04-18 | 2028 | Manager of Design Survey | IB23-016 | Sep 1, 2027 | Jun 1, 2028 |
| AB-532 |
Design Registration Requirements for Application Specific Pneumatic Test Procedures | 2 | 0 | 2024-10-10 | 2029 | Design Survey Manager | IB24-010 | Sep 1, 2028 | Jun 1, 2029 |
| AB-538 |
Integrity Management Requirements For Mechanical Refrigeration Systems Containing Ammonia | 2 | 0 | 2023-05-05 | 2028 | Manager of Inspections | IB23-020 | Sep 1, 2027 | Jun 1, 2028 |
| Examination & Certification- 1. Power Engineer Certification (AB-500 Series) | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Form. No. | Document Name | Current Edition No. | Current Revision No. | Current Publication Date | Next Scheduled Reaffirmation | Responsible Position | Enabling Information Bulletin | Public Consultation Link | Public Consultation Disposition Link |
| AB-528 |
Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems and Heating Plants | 4 | 1 | 2023-02 | 2027 | VP Technical Services | IB23-003 | Sep 1, 2026 | Jun 1, 2027 |
| AB-533 |
Power Engineering Course Acceptance Criteria | 2 | 0 | 2020-01 | 2024 | Manager of Examination & Certification | IB19-015-R1 | - | - |
| Quality Management Systems(QMS) (AB-500 Series) | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Form. No. | Document Name | Current Edition No. | Current Revision No. | Current Publication Date | Next Scheduled Reaffirmation | Responsible Position | Enabling Information Bulletin | Public Consultation Link | Public Consultation Disposition Link |
| AB-512 |
Owner-User Pressure Equipment Integrity Management Requirements | 4 | 0 | 2025-10-14 | 2030 | Manager of Inspections | IB25-015 | Sep 1, 2029 | Jun 1, 2030 |
| AB-512a |
Owner-User PEIM Program Scope and Responsibilities | 0 | 0 | 2025-10-14 | 2030 | Manager of Inspections | N/A | Sep 1, 2029 | Jun 1, 2030 |
| AB-512b |
Integrity Management Requirements Checklist | 0 | 0 | 2026-06-23 | 2031 | Manager of Inspections | N/A | Sep 1, 2029 | Jun 1, 2030 |
| AB-512c |
PEIM Audit Workbook | 0 | 0 | 2025-10-14 | 2030 | Manager of Inspections | N/A | Sep 1, 2029 | Jun 1, 2030 |
| AB-512H |
Harmonized Requirements for Pressure Equipment Integrity Management Systems | 1 | 1 | 2026-07-13 | 2027 | Manager of Inspections | IB26-004 | Sep 1, 2026 | Jun 1, 2027 |
| AB-515 |
Quality Management System Requirements for Integrity Assessment Organizations | 3 | 0 | 2022-09-19 | 2027 | Manager of Inspections | IB22-013 | Sep 1, 2026 | Jun 1, 2027 |
| AB-515a |
Integrity Assessment Organization Authorized Scope Form | 0 | 0 | 2022-09-19 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-515b |
Integrity Assessment QMS Written Description Checklist | 0 | 0 | 2026-06-23 | 2031 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-518 |
Pressure Piping Construction Requirements Document | 9 | 0 | 2022-09-19 | 2027 | Manager of Inspections | IB22-014 | Sep 1, 2026 | Jun 1, 2027 |
| AB-518b |
Pressure Piping QMS Written Description Verification Checklist | 0 | 0 | 2026-07-17 | 2031 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-524 |
Pressure Relief Devices Requirements Document | 8 | 0 | 2026-07-09 | 2031 | Manager of Inspections | IB26-001 | - | - |
| AB-524b |
PRD QMS Written Description Certification Checklist | 0 | 0 | 2026-06-23 | 2031 | Manager of Inspections | N/A | - | - |
| AB-540 |
Quality Management System Requirements for Welder Performance Qualification Testing | 1 | 2 | 2026-07-13 | 2027 | Manager of Inspections | IB26-005 | Sep 1, 2026 | Jun 1, 2027 |
| AB-540a |
WPQ Testing Scope and Responsibilities | 1 | 0 | 2026-08-07 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-540b |
Welder Performance Qualification Testing Requirements QMS Manual Checklist | 0 | 0 | 2026-06-23 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-541 |
Quality Management System Requirements for Pressure Fitting Construction | 1 | 2 | 2026-07-13 | 2027 | Manager of Inspections | IB26-003 | Sep 1, 2026 | Jun 1, 2027 |
| AB-541a |
Pressure Fitting Construction Requirements QMS Manual & Audit Checklist | 0 | 0 | 2026-06-23 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |
| AB-541b |
Pressure Fitting Construction Requirements QMS Manual & Audit Checklist | 0 | 0 | 2026-06-23 | 2027 | Manager of Inspections | N/A | Sep 1, 2026 | Jun 1, 2027 |