Pressure Piping Design Registration

As defined in the Pressure Equipment Safety Regulation (AR 49/2006) section 1 (1)(aa), "pressure piping system" means pipe, tubes, conduits, fittings, gaskets, bolting and other components that make up a system for the conveyance of an expansible fluid under pressure and may also control of the flow of that fluid.

Note that a pressure piping system is all the pressure piping being installed on a project. Separate fluid systems, such as instrument air or process gas, are not treated as individual pressure piping systems.

When is registration of a pressure piping design required?

  1. Design registration is required when the owner of the design, or the fabricator, or the contractor, or the plant owner intends to construct in Alberta for use in Alberta a pressure piping system to contain an expansible fluid at a pressure in excess of 103 kPa and when that pressure piping system has an aggregate internal capacity of more than 0.5 cubic metre;
  2. Design registration is required when the owner of the design, or the fabricator, or the contractor, or the plant owner proposes to add or modify over 0.5 cubic metre of piping as described above to the existing plant.

Note:

  • For a new pressure piping system, or an addition or modification not exceeding 500 litres, the contractor still has to complete a Construction Data Report for Piping Systems, Form AB-83. The owner/user must retain the completed form in his file for at least 5 years; permanent retention is recommended. Upon completion of a pressure piping project, the contractor shall complete a Completion of Construction Declaration, Form AB-81, and submit the signed form to ABSA.

    Note: There may be some variation to this last requirement for Owner/User companies.

  • Skid units, even with piping volumes less than 500 litres in themselves, when they are a part of a pressure piping installation exceeding a total volume of 500 litres, shall be registered.

  • Refer to section 4(2) of the Pressure Equipment Safety Regulation (AR/2006) for a partial exemption for some piping - small bore, moderate temperature & pressure, specified fluid services.

  • Hydrogen and CNG refuelling station piping shall be registered regardless of its volume.

  • ERCB's Reference Tool for interpreting Jurisdictional Relationships for Pipeline, Pressure Equipment, and Pressure Piping.

  • Note: ABSA is not in a position to receive electronic submissions.

For detailed information regarding pressure piping registration, refer to the Guidelines for Registration of Pressure Piping.

Go To Top

Updated Mar 21, 2011




Advanced Search

                                              
  
Acts and Regulations
  
Alerts and Information Bulletins
  
AB-508, Safety Codes Act Flow Chart
  
AB-31, Design Registration Application
  
AB-81, Completion of Construction Declaration
  
AB-83, Construction Data Report for Piping Systems
  
AB-83F, Construction Data Report for Piping Systems Manufactured Outside Alberta
  
AB-96, General Engineering Requirements
 
AB-96a, Guide for Completing AB-96
 
AB-520, Finite Element Analysis (FEA) Requirements
  
AB-525, Overpressure Protection Requirements for Pressure Vessels and Pressure Piping
  
Pneumatic Testing Presentation
  
Fee Schedule